SHANA - The main topsides of B13 Platform and D13 Satellite Platform of South Pars Gas Field were simultaneously loaded at Bushehr Yard of Iran Marine Industrial Company (SADRA).

According to Pars Oil and Gas Company (POGC), Payam Motamed, operator of Phase 13, said the structures were loaded on FLB 124 barge in the Persian Gulf coast on Tuesday and Wednesday.

He said domestic experts carried out all the designing and manufacturing stages of construction of the 2,200-ton platforms.

Motamed said each of the platforms are built for production of 500 million cubic feet of natural gas from the joint offshore gas field.

Iran shares South Pars gas field with Qatar in Persian Gulf waters.