SHANA - The operator of South Pars Phase 14 Development Project said gas recovery from the second offshore platform of the project had started.
According to Pars Oil and Gas Company (POGC), Hamid Reza Masoudi said on Saturday that the second platform of the phase had come online and gas recovery had started from the offshore structure.
The platform ...
SHANA - Operator of South Pars Phase 14 development says the offshore section of the project will be complete by the end of the current Iranian calendar year which began on March 21.
Hamid Reza Masoudi said the first offshore platform of the project will be launched by late May this year.
He further said that the project has so far made 80% progress ...
Shana-- The offshore section of South Pars 19 Project is now complete as its last platform was installed on Sunday.
Topside 19B, weighting 1,640 tons, was successfully installed on the jacket of the platform.
This was the last structure belonging to the offshore section of South Pars 19 that can recover up to 14.2 mcm/d of gas.
The platform ...
TEHRAN, Oct. 04 (MNA) Time has been ticking for South Pars 19th phase since the construction phase and now it would contribute to national gas production a hefty amount of 14 million cubic meters daily.
Pars Oil and Gas Co. public relations office informed Mehr News on Tuesday that only days had to be elapsed so that the 19th phase entered operation;...
Tehran, July 17 (Shana) Operator of the South Pars Phase 19 Hamid-Reza Masoodi said on Saturday that gas recovery from South Pars phase 19 has reached 800 million cubic feet a day.
Masoodi told reporters that thus far, 650,000 barrels of gas condensates of the field have been exported to target markets.
He made the remark after successful ...
TEHRAN, June 18 (Shana) Operator of phase 19 development project of the supergiant South Pars Gas Field said the phase's first gas condensate cargo will be exported within the next few weeks.
Hamidreza Masoudi said the phase has so far injected over 100 mcm of gas to the national gas network.
Phase 19 is one of a series of projects dubbed at ...
TEHRAN, Nov. 18 (Shana) Iran has finished installation of platform 19C of South Pars phase 19 to bring production from SPD2 platform to 0.5bcf by winter, operator of the phase said.
Hamid Reza Masoudi said installation of the offshore platform of phase 19 by an Iranian installer at its designated place was completed on Tuesday, November 17, 2015....
TEHRAN Sept. 22 (Shana) -- Operator of Phase 19 development of South Pars gas field says SPD 19C platform of the phase is now complete and 500 million cubic feet/day of the phase's sweet gas will be injected to the national gas trunkline for meeting the domestic demand for gas supplies in the cold.
Hamid-Reza Masoudi said the platform will be loaded ...
TEHRAN June 30 (Shana)--Phase 19 development of the massive South Pars gas field has made 86.6% progress, says the operator of the phase.
Hamid Reza Masoudi said the physical progress of the projects crossed 86% in autumn as a new platform was installed at the phase.
He further said the land, drilling and platform installations of the phase have ...
[caption id="attachment_151370" align="alignright" width="182"] Phase 12 in south eastern block of South Pars Gas Field[/caption]
TEHRAN March 19(Shana)--Phase 19 of the massive South Pars gas field is 85.5% complete, the official in charge of the development project said.
Hamid-Reza Masoudi said well drilling at Phase 19 of the offshore field,...
TEHRAN Jan 12(Shana)--Drilling operations have been completed in Phase 19 of the massive offshore South Pars gas field, contractor of the project said.
Hamid-Reza Masoudi said all wells in platforms 19A and 19C have been drilled.
He added that development of Phase 19 is ahead of other phases in terms of designing and installation in the offshore ...